City of Dubuque’s 2025 Asphalt Overlay Program Now Underway

Dubuque Road Work

The City of Dubuque’s annual asphalt overlay program is now underway and will improve just less than 10 centerline miles on 42 city streets or street sections during the 2025 construction season.

The program targets streets that would benefit from an asphalt overlay to extend the life of the existing pavement. The streets involved in the 2025 program will receive their first repaving in at least twelve years. The City of Dubuque Public Works Department manages the program which includes milling and/or grinding the existing pavement surface, recycling the old asphalt, and repaving streets for a safer and smoother ride.

Unlike street reconstruction projects, property owners are not assessed for costs associated with the asphalt overlay program. Instead, the program is funded with money collected from Iowa’s Road Use Tax Fund.

The asphalt overlay program is part of the City’s yearly street maintenance activity, which is budgeted as $1.16 million for fiscal year 2026 and includes approximately $750,000 to bring curb ramps up to ADA compliance along the overlaid streets.

——

The following is a schedule outlining when individual streets are expected to receive a partial or complete asphalt overlay this construction season:

Phase One: May

Phase Two: June

Phase Three: June-July

Phase Four: July

Phase Five: August-September

Phase Six: August-September

Phase Seven: September

The schedule of projects is available online at www.cityofdubuque.org/asphaltoverlay and will be updated as details are available.

Residents will be notified by mail prior to the start of the project with contact information and parking instructions. Normally, projects can be completed in one week and streets can be driven on soon after paving takes place and as soon as traffic control devices have been removed.

For more information, contact the public works department at 563-589-4250 or visit www.cityofdubuque.org/publicworks